# Cost as a CI/CD Gate

## Why this matters

Every module so far reacts to cost *after* it's incurred: Cost Analysis shows last
month, budgets alert once spend crosses a line, showback reports what already
happened. Even the fastest of these is a monthly or daily feedback loop — and by
then the money is spent and the Terraform is already applied. This module closes the
loop at the earliest possible point: **the pull request**. By estimating the cost of
an infrastructure change *from its Terraform plan* and posting it as a **PR comment**
— and enforcing hard **cost guardrails as policy** — you show engineers the price of
a decision *while they're still making it*, exactly the "shift left" instinct behind
tracks 10, 11, and 17. This is the culmination of module 00's culture shift: cost
becomes a checked, visible property of every change, like tests and security scans
already are.

## Concepts

### Shift cost left: from month-end to the pull request

The core idea is **shifting cost feedback left** — moving it from the end of the
lifecycle (the bill) to the beginning (the code review), the same move you already
made for **tests** (track 10), **security scanning** (track 11), and **policy**
(track 17). A cost estimate at PR time is worth more than a perfect report at
month-end for one reason: **it reaches the engineer at the moment the decision is
cheap to change.** Adding `node_count = 10` or bumping a disk to Premium in a
Terraform PR is a one-line edit to reconsider *before* merge; the same change
discovered on next month's bill is a deployed, running, argued-over cost. The whole
Inform-phase premise (module 00 — "put the number where the decision is made") hits
its sharpest point here: the PR diff is where infrastructure cost is *born*, so it's
where the number belongs.

### Infracost: cost from a Terraform plan

**Infracost** is the standard open-source tool for this. It reads a **Terraform
plan** (the `terraform plan` output from track 09 — the same plan you learned to
*read* the `N to add` from) and produces a **cost estimate** by pricing each
resource the plan would create/modify against cloud pricing data. It works because a
Terraform plan is a **precise, declarative statement of exactly what will exist** —
SKUs, sizes, counts, regions — which is exactly what you need to price it. Infracost
runs in two main modes: **`infracost breakdown`** (the full estimated monthly cost of
a configuration) and **`infracost diff`** (the *delta* a change introduces — "this PR
adds \$340/month"), which is the one that belongs in a PR. Key honesty about what it
can and can't do:

- It estimates **usage-independent** costs well (a VM's hourly rate, a disk's
  provisioned size, a fixed node count) — the things the plan pins down.
- It **can't** know **usage-based** costs (data egress, requests, storage
  *consumed*, function invocations) without a **usage file** you provide with
  assumptions — so its estimate is a **projection under stated assumptions**, not a
  guaranteed bill. This is the same caveat as module 01's forecasts, just at
  plan-time.

The value isn't a to-the-cent bill; it's a **directionally-correct, per-PR delta**
that catches the accidental 10x before it merges.

### Wiring it into CI (tracks 09/10)

The gate lives in the **CI pipeline** you built in **track 10** (GitHub Actions /
the CI system), operating on the **Terraform** from **track 09**. The pattern, on
every PR that touches infrastructure:

1. `terraform init` and `terraform plan -out=plan.tfplan`, then `terraform show
   -json plan.tfplan > plan.json` — the machine-readable plan (track 09).
2. `infracost breakdown --path plan.json` on the PR branch and on the base branch —
   or `infracost diff` — to compute the **cost delta**.
3. **Post the delta as a PR comment** (Infracost's GitHub/GitLab integration, or a
   step that comments), so reviewers see "+\$340/month" right next to the code diff.
4. Optionally **fail the check** if the delta exceeds a threshold (see guardrails).

This is deliberately the same shape as the test/scan/policy steps already in your
pipeline (track 10) and the signing/SBOM gates (track 18) — cost is just another
**automated check** on the change. Infracost needs an API key (free tier available)
for pricing data, stored as a CI secret (track 10's secrets handling / track 16).
Because it runs on a *plan*, it never touches real infrastructure — the estimate is
free and safe.

### Cost guardrails as policy (tracks 11/17)

A PR comment *informs*; a **guardrail** *enforces*. Two complementary layers, both
reusing machinery you already have:

- **Threshold gates in CI** — fail the PR check if the cost **diff exceeds a limit**
  (e.g. ">\$500/month increase requires approval"), using Infracost's **policy
  support** (it can evaluate policies written in **OPA/Rego** — the *same*
  policy-as-code engine you met for admission control in track 11 and could apply
  to infra). This makes an expensive change a **blocking, override-with-approval**
  event, not a silent merge.
- **Preventive Azure Policy** — deny the expensive thing *at deploy time* regardless
  of pipeline, using **Azure Policy** from **track 17** (and track 11): deny VM SKUs
  above a size in dev, deny Premium disks in non-prod, restrict regions, require a
  lifecycle policy on storage (module 04). This is the **defense-in-depth** you
  already understand — the CI gate catches it in review, and Azure Policy catches it
  even if someone bypasses CI (a portal click, a rogue `terraform apply`). The CI
  gate is *fast feedback*; Azure Policy is the *hard backstop*.

The design principle is the track-11/17 one: **guardrails, not gates that block
everything** — the goal is to make the *expensive path require a conscious,
approved decision*, not to forbid spending. A gate that fails on every \$5 increase
gets disabled; a gate that flags a \$2,000/month jump for a human to approve gets
respected.

### The estimate is directional — treat it as a signal, not a contract

The failure mode that discredits the whole practice is **over-trusting the number**.
Infracost's estimate is a **projection under assumptions** — it prices what the plan
declares, applies default or usage-file assumptions for consumption, and can't see
runtime reality (autoscaling that never triggers, a spot discount from module 05, an
existing reservation, real egress). So the estimate can be **materially off** on
usage-heavy resources, and someone will eventually "catch it being wrong" and argue
the gate is worthless. The correct framing (and the honest one): the gate's job is to
**catch the direction and the order of magnitude** — the accidental `count = 100`,
the Premium-disk-in-dev, the forgotten always-on cluster — *before* merge, and to
make cost **visible and discussed** in review. It is a **signal that prompts a
conversation**, not a contract that predicts the invoice. Tune the threshold so it
fires on changes worth a human look, feed it a realistic usage file for your big
consumption resources, and pair it with the *actual* post-deploy cost tracking
(modules 01-02) that measures what really happened. Plan-time estimate + post-deploy
measurement is the full loop; the estimate alone is only half.

## Command reference

Infracost runs on a Terraform **plan** — it never touches real infrastructure, so
these are **free and safe**. The Azure Policy commands reuse track 17.

| Command | What it does | Example |
|---|---|---|
| `infracost auth login` | Authenticates Infracost (free tier) for pricing data | `infracost auth login` |
| `infracost breakdown --path <dir\|plan.json>` | Full estimated monthly cost of a config/plan | `infracost breakdown --path plan.json` |
| `infracost diff --path <plan.json>` | The **cost delta** a change introduces (the PR number) | see breakdown below |
| `infracost comment github` | Posts the estimate as a PR comment (CI integration) | `infracost comment github --path infracost.json --repo <r> --pull-request <n> --github-token $GH` |
| `terraform show -json plan.tfplan` | Converts a saved plan to JSON for Infracost (track 09) | `terraform plan -out=tf.plan && terraform show -json tf.plan > plan.json` |
| `infracost breakdown --usage-file <f>` | Prices usage-based resources using your stated assumptions | `infracost breakdown --path plan.json --usage-file usage.yml` |
| `az policy assignment create` (deny SKU/tier) | Preventive Azure Policy backstop (tracks 11/17) | `az policy assignment create --name deny-premium-dev --policy <def> --scope <dev-scope>` |

Flag breakdown — the PR-time cost diff, the heart of the gate:

```bash
infracost diff \
  --path plan.json \
  --compare-to infracost-base.json \
  --format json \
  --out-file infracost.json
```

- `--path plan.json` — the **PR branch's** Terraform plan (JSON via `terraform show
  -json`, track 09) — what the change *would* create.
- `--compare-to infracost-base.json` — the **base branch's** prior Infracost
  breakdown; the diff between them is the **delta this PR introduces** ("+\$340/mo").
- `--format json --out-file infracost.json` — machine-readable output the next step
  (`infracost comment` / a policy check) consumes to post the comment and/or
  enforce the threshold.

Flag breakdown — an Infracost policy that fails the check on a big increase (OPA/Rego, track 11 engine):

```bash
infracost breakdown --path plan.json --format json --out-file infracost.json
infracost comment github --path infracost.json --policy-path cost-policy.rego \
  --repo org/repo --pull-request 42 --github-token "$GITHUB_TOKEN"
```

- `--policy-path cost-policy.rego` — a **Rego** policy (the same policy-as-code
  language as track 11's admission control) evaluated against the estimate — e.g.
  "fail if `diffTotalMonthlyCost > 500`". This is what turns the comment into a
  **blocking guardrail**, overridable with an approval.
- `--repo` / `--pull-request` / `--github-token` — where to post and how to
  authenticate (a CI secret, track 10/16), so the result lands on the PR.

## Hands-on exercises

Infracost runs on a plan, so everything here is **free and touches no real
infrastructure**. Reuse a Terraform config from **track 09** (or write a tiny one).
You'll need a free Infracost API key.

1. **Install and authenticate Infracost.** Install the CLI (per its docs) and run
   `infracost auth login` for a free API key. Confirm with `infracost --version`.
   Note it needs only pricing data — no Azure credentials, because it prices a
   *plan*, not live resources.

2. **Break down a real Terraform config.** Point Infracost at a track-09 config:
   ```bash
   cd <your-track-09-terraform-dir>
   terraform init
   terraform plan -out=tf.plan
   terraform show -json tf.plan > plan.json
   infracost breakdown --path plan.json
   ```
   Read the per-resource monthly estimate. Note which resources it prices
   confidently (VMs, disks — usage-independent) and which show `Monthly cost depends
   on usage` (egress, requests). That split is the whole "directional, not exact"
   lesson made visible.

3. **Compute a cost diff for a change.** Edit the config to make something more
   expensive (bump a VM SKU, add `count`, switch a disk to Premium). Re-plan, then:
   ```bash
   infracost diff --path plan.json
   ```
   Read the "+\$X/month" delta. *This* number — the delta a change introduces — is
   what belongs in a PR, far more actionable than an absolute total.

4. **Provide a usage file for a consumption resource.** For a resource whose cost
   `depends on usage`, create an `infracost-usage.yml` with an assumption (e.g.
   monthly egress GB, request count) and re-run `infracost breakdown --path plan.json
   --usage-file infracost-usage.yml`. Watch the previously-unknown cost become an
   estimate. Write down: this number is only as good as your assumption — a
   projection, not a promise (the module 01 forecast caveat, at plan time).

5. **Catch an accidental 10x.** Deliberately introduce the classic mistake — change
   a node/replica `count` from `2` to `20`, or a size an order of magnitude too big.
   Run `infracost diff` and see the delta explode. This is exactly what the PR gate
   exists to surface *before* merge — the accidental blowout caught in review, not on
   the bill.

6. **Wire it into CI (design or real, track 10).** In a GitHub Actions workflow (or
   your track-10 CI), add a job on infrastructure PRs that runs
   `terraform plan` → `terraform show -json` → `infracost diff` → `infracost comment
   github`, storing the Infracost API key as a **CI secret** (track 10/16). If you
   have a repo handy, wire it for real and open a PR to see the comment; otherwise
   write the workflow YAML and explain each step's place in the pipeline (same shape
   as your test/scan steps).

7. **Add a threshold guardrail as policy (track 11 engine).** Write a small Rego
   policy that fails the check when the monthly diff exceeds a threshold (e.g.
   \$200), and attach it via `--policy-path`. Test it against your exercise-5
   blowout (fails) and a trivial change (passes). Note this is the *same*
   policy-as-code language you used for admission control in track 11 — now guarding
   cost instead of security.

8. **Add the preventive Azure Policy backstop (track 17).** Design (or assign) an
   Azure Policy that **denies** an expensive choice at deploy time — e.g. deny
   Premium disks or oversized VM SKUs in a `dev`-tagged scope (reusing the tag from
   track 17 module 06 and the `Deny` effect from track 11 module 05 / track 17
   module 03). Write down why you want *both* this and the CI gate: the CI gate is
   fast feedback in review; Azure Policy is the hard backstop that catches a
   portal-click or a CI bypass.

9. **Diagnose and fix: the cost gate everyone ignores (or games).** The
   discredited-gate failure mode. Scenario: the team wired an Infracost gate that
   **fails the build on any increase over \$5/month**. Within a week, engineers are
   routinely overriding it, or worse, someone "proved it wrong" (it estimated
   \$400 for a resource whose real bill was \$90 because autoscaling never triggered),
   and now nobody trusts it. **Diagnose:** two coupled problems — the **threshold is
   too low** (it fires on trivial changes, training people to override reflexively),
   and the estimate was **over-trusted as exact** on a usage-heavy resource where
   Infracost can't see runtime reality (autoscaling/spot/reservations). **Fix:** (a)
   **raise the threshold** to a level worth a human's attention (flag changes big
   enough to matter, e.g. >\$200-500/mo, requiring approval — a guardrail, not a
   tollbooth — the track-11/17 principle); (b) reframe the number as a
   **directional signal** that prompts a conversation, not a contract; (c) feed a
   realistic **usage file** for the big consumption resources so estimates are less
   wrong; and (d) **pair it with post-deploy actuals** (modules 01-02) so real cost
   is measured, not just estimated. Lesson: **a cost gate that blocks everything or
   claims to predict the invoice gets disabled; a guardrail that flags the changes
   worth discussing, framed as a signal and backed by real measurement, gets
   respected.**

10. **(No cleanup needed.)** Infracost created no real resources. If you assigned a
    real Azure Policy in exercise 8, remove it (`az policy assignment delete`) unless
    you want to keep the guardrail.

## Independent challenge

No commands given. Drawing on this module, the Terraform from **track 09**, the CI
pipeline from **track 10**, the policy-as-code (OPA/Rego admission control) from
**track 11**, the Azure Policy `Deny` and tagging from **track 17** (modules 03/06),
and the post-deploy cost tracking from **modules 01-02**, build a **complete
cost-gate for an infrastructure repo**. It must: run **Infracost on every
infrastructure PR** and post the **monthly cost diff** as a PR comment; enforce a
**threshold guardrail** (a Rego policy that requires approval above a sensible
limit — justify the number, not \$5); include a **preventive Azure Policy** backstop
that denies at least one expensive choice at deploy time (tied to the `Environment`
tag); provide a **usage file** so at least one consumption-based resource is
estimated rather than "depends on usage"; and be **defended in writing** as
*defense-in-depth* — what the CI gate catches, what Azure Policy catches, and why you
need both. Finish with two or three sentences on how you'd **close the loop** by
comparing the plan-time estimate to the *actual* post-deploy cost (modules 01-02),
and why the estimate alone is only half the practice. The deliverable is the pipeline
config, the policies, and the written defense.

<details>
<summary>Stuck? One hint</summary>

Build it as *just another CI check*, structurally identical to the test and security
steps already in your track-10 pipeline: on an infra PR, `terraform plan` →
`terraform show -json` → `infracost diff --compare-to <base>` → `infracost comment
github`. The threshold is the design decision people get wrong — set it where a
human *should* look (a few hundred dollars a month, requiring approval), not where
every change trips it, or you recreate exercise 9's ignored gate. For
defense-in-depth, remember the CI gate is **fast feedback in review** but bypassable
(portal clicks, a manual apply), while **Azure Policy** (track 17 module 03 / track
11 module 05) is the **unbypassable deploy-time backstop** — deny Premium disks or
oversized SKUs on the `Environment=dev` scope using the tag from track 17 module 06.
And keep the estimate honest: it's directional, so pair the plan-time number with
the actual post-deploy cost from modules 01-02 — that comparison is what makes the
whole gate trustworthy over time.

</details>

## Common mistakes & troubleshooting

- **Setting the threshold too low.** A gate that fails on every trivial increase
  trains engineers to override reflexively and then it's decoration. Flag changes
  worth a human's attention (hundreds/month, requiring approval) — a guardrail, not
  a tollbooth (tracks 11/17).
- **Treating the estimate as an exact bill.** Infracost prices what the plan
  declares under stated assumptions; it can't see autoscaling, spot (module 05),
  reservations, or real egress. Frame it as a **directional signal**, and it stays
  credible.
- **Not providing a usage file.** Usage-based resources show "depends on usage" and
  get ignored, or default assumptions mislead. Supply realistic usage for your big
  consumption resources so their estimates mean something.
- **CI gate *or* Azure Policy, not both.** The CI comment is fast feedback but
  bypassable; Azure Policy is the deploy-time backstop but has no PR context. You
  need both — defense-in-depth (tracks 11/17).
- **Running Infracost against live infra instead of a plan.** It works off the
  Terraform **plan JSON** (track 09). Feed it `terraform show -json`, not live
  resources — that's why it needs no Azure credentials and touches nothing.
- **Estimate without post-deploy measurement.** A plan-time estimate is half the
  loop; without comparing to *actual* cost (modules 01-02) you never learn how wrong
  it was, and the gate can't be tuned. Close the loop.
- **Leaking the Infracost API key.** It's a CI secret (track 10/16) — never commit
  it. It's only pricing-data auth, but still handle it like any secret.

## Checkpoint quiz

Write down your answer to each question before expanding it — checking without attempting first is the single easiest way to fool yourself into thinking you've learned this.

<details>
<summary>Show questions</summary>

1. What does "shifting cost left" mean, and why is a cost estimate at PR time worth
   more than a perfect report at month-end?
2. What input does Infracost read, why does that input make cost estimation
   possible, and which track taught you to read that same artifact?
3. Which costs does Infracost estimate well, which does it struggle with, and what do
   you provide to help with the latter?
4. Describe the CI pipeline steps that turn a Terraform PR into a cost comment
   (tracks 09/10). Does Infracost touch real infrastructure?
5. What are the two guardrail layers (CI threshold vs. Azure Policy), which track
   provides each, and why do you want both?
6. Why is the Infracost estimate "directional, not a contract," and what's the
   failure mode of over-trusting it?
7. How should you set the cost-diff threshold so the gate gets respected rather than
   disabled, stated as the track-11/17 principle?
8. What's the "other half" of the loop that a plan-time estimate alone is missing,
   and which modules provide it?

</details>

<details>
<summary>Show answers</summary>

1. Moving cost feedback from the end of the lifecycle (the bill) to the start (the
   PR/code review) — the same shift as tests (track 10), scanning (track 11), policy
   (track 17). It's worth more because it reaches the engineer **when the decision is
   still cheap to change** (a one-line edit before merge vs. a deployed, argued cost).
2. A **Terraform plan** (JSON via `terraform show -json`, track 09). The plan is a
   precise declarative statement of exactly what will exist — SKUs, sizes, counts,
   regions — which is exactly what's needed to price it. Track 09 taught you to read
   the plan's `N to add`.
3. It estimates **usage-independent** costs well (VM rates, disk provisioned size,
   fixed counts). It struggles with **usage-based** costs (egress, requests, consumed
   storage, invocations); you provide a **usage file** with assumptions to estimate
   those (making it a projection under assumptions).
4. `terraform init` → `terraform plan -out` → `terraform show -json` → `infracost
   diff` (vs. the base branch) → `infracost comment` posts the delta on the PR
   (track 10 CI, track 09 Terraform). It runs on the **plan**, so it touches **no
   real infrastructure** and needs no Azure credentials.
5. A **CI threshold gate** that fails the PR check above a limit (Infracost + OPA/Rego
   — track 11's policy engine), and **preventive Azure Policy** that denies expensive
   choices at deploy time (track 17 / track 11 `Deny`). Both because the CI gate is
   fast review feedback but bypassable, and Azure Policy is the unbypassable
   deploy-time backstop — defense-in-depth.
6. Because it prices what the plan declares under stated assumptions and can't see
   runtime reality (autoscaling, spot, reservations, real egress), so it can be
   materially off on usage-heavy resources. Over-trusting it means someone "proves it
   wrong" and the whole gate loses credibility — it's a signal, not the invoice.
7. Set it where a human **should** look — flag changes big enough to matter
   (hundreds/month), requiring approval — not where every trivial change trips it.
   The track-11/17 principle: **guardrails that make the expensive path a conscious,
   approved decision**, not gates that block everything (which get disabled).
8. **Post-deploy actual cost measurement** — comparing the plan-time estimate to what
   really got billed — from **modules 01-02** (Cost Analysis and budgets). The
   estimate is only half the loop; measuring actuals is how you learn how wrong it
   was and tune the gate.

</details>

## Next

Continue to
[08-capstone-project](../08-capstone-project/README.md)
— you've now built the full FinOps practice: the framework (module 00), visibility
and allocation (01), budgets (02), the Optimize levers (03-05), showback (06), and
the shift-left cost gate (this module). The capstone asks you to run all of it, for
real, against your own subscription — one cost analysis, one firing budget, one
measured rightsizing, one orphaned-resource sweep, and one cost gate in a PR — and
prove each with evidence.